Locking Current Period Retention on an Existing Subcontract

To lock retention on an existing subcontract:

  1. Access the Edit Contract dialog box from the Subcontract List page or the Contract Maintenance page.
    1. From the Subcontract List page, select the Action icon and select Edit Settings.
    2. From the Contract Maintenance page, select Edit Settings button.
  2. (Optional) In the Default Retention % field, change the amount of retention to be held for this period and the remaining billing periods.
  3. Select the subcontractor cannot modify retention setting.
  4. Save your changes.