Removing Component Level Retention Overrides on a Contract
To remove a retention override:
- Navigate to the Contract Maintenance Page
- From the Subcontract List page, select the Pencil icon.
- From the Edit Contract tab of the Edit Schedule of Values page, select the New link to go to the Contract Maintenance page for a new subcontract.
- From the Retention tab on the Contract Maintenance page, select the Clear all retention overrides check box.
- Select the Save Changes button.
- A Status page confirms the contract has been saved.
- When the Subcontractor enters an invoice for the next draw, the application holds the default retention for all components.