Viewing Critical Path Activities

From the Gantt view, you can quickly identify all tasks that are on the critical path. The tasks that can directly impact a project’s end date are displayed in red.

To view activities on the critical path:

  1. From the Project Roadmap, select the Gantt tab.
  2. Click the check box Show Critical Path.

Tip:

If no critical path displays, check to see if you have set too much slack in the project schedule.

See Also

Using the Gantt View