Release Project Resource Allocation

You can release a project resource allocation after the resource allocation has been approved. You can choose to release for the entire duration or for a partial duration of the project.

Note: You must have appropriate permissions to release a resource allocation.

To release a resource allocation, do the following:

  1. Navigate to the Resources page by selecting Project Module Menu (Project #)> Go To > Resources or by clicking the Resources link on the Left Navigation Bar within a particular project.
  2. Select a resource allocation and select > Release.
  3. Select if you want to release the allocation for the entire duration or release the allocation for a partial period.
  4. Enter the modified allocation dates by clicking on the Calendar icon, if you selected to release partial allocation.
  5. A list of activities is displayed if they were assigned to this resource. You have the option to unassign all activities associated with the resource by checking the Unassign box.
  6. Enter a reason for releasing this project resource allocation.
  7. Click the Release.

    Note: Only Project Managers with appropriate permissions can unassign activities.

Related Topics

Working with Project Resources

Assigning Resources to a Project

Re-assigning a Team Member to a Role

Reassigning an Activity

Reassigning a Team Member

Edit Team Member Information

View Rate Change History

Using the EnterpriseTrack Email client

Using an External Email Client

Managing Your Team Picture

Deleting a Team Picture

Working with Resource Assignments

Create Request for Resource Allocation

Edit a Resource Allocation Request

Withdraw a Request for Resource Allocation

Reopen Resource Allocation Request

View a Team Member's Calendar



Legal Notices | Your Privacy Rights
Copyright © 2000, 2020

Last Published Tuesday, June 9, 2020