Configure Gantt chart options to determine how the chart will display.
To configure Gantt chart options:
- Click Projects.
 - On the Projects navigation bar, click Activities.
 - On the Activities page:
- Click Customize View.
 - In the Manage View dialog box, click the Gantt tab.
 - On the Gantt tab:
- Select the Data date line option to show the data date on the Gantt.
 - Select the Relationship lines option to show lines between activities on the Gantt.
 - Select the Non-driving relationships option to draw lines between activities on the Gantt even where the relationship doesn't affect the successor's dates.
 - Select the Sight Lines option to show vertical lines between each segment of the timescale.
 - Select the Non-work time shading option to have non-work time shaded on the Gantt.
 - Select a Timescale.
 
 - Click Apply.
 
 
Tips
- The Gantt chart only prints if it is displayed.
 - You can right click on the timescale to change the timescale of the Gantt.