Adding Activity Resource Estimates

You can plan resource usage by adding resource estimates to activities.

To add resource estimates:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, select an activity and click the Assignments detail window.
  4. In the Assignments detail window:
    1. Assign a resource or role to the selected activity.
    2. Add the Planned Units/Time, Planned Units, Planned Cost, and Planned Duration columns to the detail window.
    3. Select an option or enter a value for each field.

Related Topics

About Resources

Assigning Resources to an Activity

Assigning Resources to Multiple Activities

Configuring Activity Resources

Specifying Resource Assignment Rates

Assigning Resource Curves to Resource or Role Assignments from the Activities Page

Assigning Resources to Unstaffed Activities

About the Recalculate Assignment Costs Feature

Configuring Resource Leveling Options and Priorities

Leveling Project Resources

About the Check Resource Overallocation Service

Available Columns of the Assignments Detail Window of the Activities Page

Assigning Resources to an Activity

Assigning Roles to an Activity

Showing or Hiding Columns in a Table



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021