Specifying Resource Assignment Rates

You can set rate information for resources or roles.

To specify resource assignment rates:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, select an activity in the table and click the Assignments detail window.
  4. In the Assignments detail window:
    1. Add the Rate Type and Rate Source columns.
    2. Select an option for the type and source.
    3. Save your changes.

Tips

When you save your changes, costs for the assignment are recalculated based on the new rate: Cost equals Units times Price/Unit. You can add the Price/Unit column to the detail window to view the price used. To manually specify a price/unit, select Override in the Rate Source field and type a value in the Price/Unit field.

Related Topics

About Resources

Assigning Resources to an Activity

Assigning Resources to Multiple Activities

Configuring Activity Resources

Adding Activity Resource Estimates

Assigning Resource Curves to Resource or Role Assignments from the Activities Page

Assigning Resources to Unstaffed Activities

About the Recalculate Assignment Costs Feature

Configuring Resource Leveling Options and Priorities

Leveling Project Resources

About the Check Resource Overallocation Service

Available Columns of the Assignments Detail Window of the Activities Page

Showing or Hiding Columns in a Table



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021