Successors Section of the Relationships Section of the Activity Form Page

Overview

Use this section to view successor relationships.

Screen Elements

Project ID field

The unique identifier of the project containing the successor activity.

Activity ID field

The unique identifying code for the successor activity.

Activity Name field

The name of the selected activity's successor.

Relationship Type list

The relationship between two activities. Select from the following types:

Finish to Start: A relationship in which the start of a successor activity depends on the completion of its predecessor activity. This is the default activity relationship.

Finish to Finish: A relationship in which the finish of a successor activity depends on the finish of its predecessor activity.

Start to Start: A relationship between activities in which the start of a successor activity depends on the start of its predecessor.

Start to Finish: A relationship between activities in which a successor activity cannot complete until its predecessor activity starts.

Lag field

The amount of time the predecessor activity was delayed, affecting the ability of its successor activity to start or finish.

This value is specified by the project manager and is used by the project scheduler when scheduling activities.

Getting Here

  1. Click Dashboards.
  2. On the Dashboards page, select a dashboard tab.
  3. On the dashboard tab, expand any portlet containing activities.
  4. In the portlet, click an activity.
  5. On the Activity Form page, expand the Relationships section

Related Topics

About Relationships

Assigning Successor Relationships

Configuring Successor Relationships