Assigning Successor Relationships

You can assign successor relationships to the activities in your project.

To assign a successor relationship:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
    1. On the Activities page, select an activity to which you want to assign successors and click the Relationships detail window.
    2. In the Relationships detail window, in the Successors area, click Add.
    3. In the Select Successor Activity dialog box, select one or more activities and click OK.
    4. On the Activities page, click Save.