You can create activity relationships in the Gantt chart to show interdependencies between activities.
To create an activity relationship:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page:
- Click Gantt View.
- Click Gantt Settings and select to show relationships.
- Hover either to the left or right of a bar.
- Drag the circle to the left or right end of a bar representing the activity you want to link.
Note: Where you drag the relationship on each bar determines the type of relationship.
- Click Save.
Tips
- You can scroll through the Gantt chart while while dragging a relationship to find a related bar.
- To delete a relationship, right-click the relationship line and select Delete Relationship.
- If multiple projects are open, you can create external relationships.
- You can also create new relationships and view or configure existing predecessor or successor relationships, from the Predecessors, Successors, or Relationships detail windows.