Configure activity relationships to adjust interdependencies between different activities.
To configure activity relationships:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page:
- Click Gantt View.
- Click Gantt Settings and select to show relationships.
- Right click the relationship line of the relationship you want to configure and click Edit Relationship.
- In the Edit Relationship dialog box, configure the type and lag and click Apply.
- On the Activities page, click Save.
Tips
You can also configure predecessor and successor relationships from the Predecessor, Successor, or Relationships detail windows.