Used By Tab of the Project Calendars Page

Overview

Use this tab to view the activities and resources assigned to projects on the project calendar.

Screen Elements

Print

Opens the Print Options dialog box.

Search

Searches the view or dialog box for data matching the criteria entered into the box.

ID field

The ID of the project, activity, or resource assigned to the calendar.

Name field

The name of the project assigned to the calendar.

Tips

Getting Here

  1. Click Administration.
  2. On the Administration navigation bar, click Enterprise Data.
  3. On the Enterprise Data page, expand Projects and click Project Calendars.
  4. On the Project Calendars page, click the Used By tab.

Related Topics

About Calendars

Creating Project Calendars

Configuring Project Calendars

Assigning a Base Calendar to a Project Calendar

Setting Work Hours Per Period for a Project Calendar

Configuring the Standard Work Week for Project Calendars

Modifying Calendar Days on Project Calendars

Changing a Project Calendar to a Global Calendar



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021