Configuring the Standard Work Week for Project Calendars

Configure the standard work week for the calendar to set the work and nonwork days and hours for a standard work week.

To configure the standard work week:

  1. Click Administration.
  2. On the Administration navigation bar, click Enterprise Data.
  3. On the Enterprise Data page, expand Projects and click Project Calendars.
  4. On the Project Calendars page:
    1. Expand a project.

      Note: If the project you need is not open, click Open Project.... Choose one or more projects and click Open.

    2. Click on the calendar you want to modify.
    3. Click the Standard Work Week tab.
  5. On the Standard Work Week tab, right-click on a working or nonworking timeslot and use the menu options to adjust the workday. You can also resize the working time to increase or decrease the work hours.
  6. Click Save (Ctrl+S).

Related Topics

Configuring Project Calendars

Assigning a Base Calendar to a Project Calendar

Setting Work Hours Per Period for a Project Calendar

Modifying Calendar Days on Project Calendars

Changing a Project Calendar to a Global Calendar

Project Calendars Page