Adding Risk Response Plans

Add one or more response plans to a risk to plan alternative activities that might reduce the probability of a risk occurring, or to reduce the impact of the risk.

  1. Click Projects.
  2. On the Projects navigation bar, click Risks.
  3. On the Risks page, click a risk, and then click the Response Plans detail window.
  4. On the Response Plans detail window:
    1. Click Add and select Response Plan.
    2. In the ID field, double-click and type a response plan ID.
    3. In the Name field, double-click and type a name for the new response plan.
    4. In the Response Type field, double-click and select a response type from the list.
  5. On the Risks page, click Save.

    Note: After you decide which response plan you are implementing, select the Active option next to the appropriate response plan.

Related Topics

About Risk Response Plans

Working with Risk Response Plans

Developing a Risk Response Plan

Adding Risk Response Plan Action Items

Assigning Activities to Risk Response Plan Action Items

Response Plans Detail Window of the Risks Page