Configure advanced scheduling options to define float paths.
To configure advanced scheduling options:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page:
- Click Schedule....
- In the Schedule dialog box, click the Advanced tab.
- On the Advanced tab:
- Select the Calculate Multiple Float Paths option.
- Select Total Float or Free Float.
- Enter or select a value for each field.
- Click Save.
Tips
- You can select any activity in the Display Multiple Float Paths ending with activity dialog box; however, typically this activity is a milestone or some other major activity in the project schedule.
- To optimize performance, type a low number (10 or less) in the Specify the number of paths to calculate field.