Configure the bar settings for the Gantt chart view on the Activities page.
To configure activity view bars:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page:
- Click Customize View
- In the Manage Views dialog box, click the Bars tab.
- On the Bars tab click Configure.
- Select a theme to use a pre-configured set of colors for bars.
- Click a bar to configure it and then:
- Click the Bar Type list and choose one of the available bar types.
- Click the Height list and choose a height for the bar.
- Select the Show Progress option to chart progress, or actual work, along the Current Bar.
Select a Progress Color, a Bar Color, and a Progress Style to determine how progress will be shown on the bar.
- Select Show Critical to determine that the bar will display differently if the activity is critical.
Note: Click the Add menu and select Bar or Label to add a new bar or label. Select a bar or label and click to delete it.
- Click a label to configure it and then:
- In the Label Field list, select a field.
- In the Color field, select a text color.
- In the Height list, select a height.
Note: Click Preview to see how the bars and labels you have configured will look when shown with other bars.
- Click Apply.
Tips
- The Gantt chart only prints if it is displayed.
- A Late Bar does not display if the project has not been scheduled.