Applying the Progress Spotlight

To quickly locate the activities you need to update, you can use the Progress Spotlight feature, which highlights all activities that should have progressed during a specific time period. This time period is defined by the smallest increment of the current timescale starting with the data date. For example, if the current timescale is set to Month/Week, Progress Spotlight highlights all activities that should have progressed during the week starting with the data date.

To show or hide the Progress Spotlight:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Click Gantt View, if the Gantt view is not selected.
    2. Click Progress Spotlight (Ctrl+Alt+S).
  4. Click Save View.