Working with Resource Assignments in the Gantt Chart

The Resources Assignments area enables you to view a customized list of resources based on the filters you assign to the view. You can extend this customized view by displaying the Gantt chart, which is a graphical display of the start and end dates for the resource assignments.

To customize the resource assignments view in the Gantt chart, you can:

Related Topics

Viewing Resource Assignments in a Gantt Chart

Configuring the Resources Assignments Gantt Chart Bars

Setting the Resources Detailed Assignments Gantt Chart Timescale

About Resource Assignments

About Assignments Views

Viewing Assignment Unit and Cost Spreads

Assigning a Resource to an Activity Assignment

Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page

About Future Period Planning