Set the timescale interval of the Gantt chart and apply shading for non-work time.
Note: If you only want to change the timescale, right-click the date bar in the Gantt chart and choose another timescale.
To set the timescale interval and apply shading for non-work time:
- Click Resources.
- On the Resources navigation bar, click Assignments.
- On the Assignments page, click Customize View.
- Click Gantt.
- On the Gantt tab:
- Click the Timescale list and select the timescale for the Gantt chart.
- Select Non-work time shading to apply shading to non-work time represented in the Gantt.
- Click Apply.
Tips:
If you select the Week/Day timescale, the following fields are not applicable: Period Actual Units, Period At Completion Units, Period Actual Cost, Period Actual Completion Cost.