Field Definitions for Dates and Work Units

The fields available to you in the progress panel are assigned by your project manager in P6. In P6, a team member is assigned as a resource assignment, an activity owner, or a user with a Team Member work distribution filter.

Resource Assignment

Finish By

The date you are scheduled to complete the activity.

Finished

The date you actually completed the activity.

Log Additional Time

The amount of time you have worked on the activity since you last reported your work.

Start By

The date you are scheduled to begin the activity.

Started

The date you actually began work on the activity.

Time Left

The total working time left to complete the activity.

Time Spent

The actual amount of time spent working on the activity.

Remaining Duration

The period of time required to complete the activity based on your current work schedule and additional project commitments.

Activity Owner or User Assigned a Team Member Work Distribution Filter

% Complete

The percentage of the activity that has been completed.

The calculation of this field depends on the settings your project manager configured in P6.

This field is either:

Expected Finish

The date you expect work on the activity to end.

Finish By

The date you are scheduled to complete the activity.

Finished

The date you actually completed the activity.

Log Additional Time

The amount of time you have worked on the activity since you last reported your work.

Remaining Duration

The period of time required to complete the activity based on your current work schedule and additional project commitments.

Start By

The date you are scheduled to begin the activity.

Started

The date you actually began work on the activity.

Time Spent (Labor)

The actual amount of time spent working on the activity.

Time Spent (Nonlabor)

The actual amount of time spent on the activity by a nonlabor resource.

Time Left (Labor)

The total working time left to complete the activity.

Time Left (Nonlabor)

The remaining time required of a nonlabor resource to complete the activity.

Step me through...

Updating Activities

Starting Activities

Completing Activities

Learn more about...

Working with Activities



Legal Notices | Your Privacy Rights
Copyright © 2011, 2020

Last Published Wednesday, December 2, 2020