The fields available to you in the progress panel are assigned by your project manager in P6. In P6, a team member is assigned as a resource assignment, an activity owner, or a user with a Team Member work distribution filter.
Resource Assignment
Finish By
The date you are scheduled to complete the activity.
Finished
The date you actually completed the activity.
Log Additional Time
The amount of time you have worked on the activity since you last reported your work.
Start By
The date you are scheduled to begin the activity.
Started
The date you actually began work on the activity.
Time Left
The total working time left to complete the activity.
Time Spent
The actual amount of time spent working on the activity.
Remaining Duration
The period of time required to complete the activity based on your current work schedule and additional project commitments.
Activity Owner or User Assigned a Team Member Work Distribution Filter
% Complete
The percentage of the activity that has been completed.
The calculation of this field depends on the settings your project manager configured in P6.
This field is either:
- Calculated using units or duration.
- Calculated using the percentage complete from steps.
- A value you enter based on your own perception of the work you completed on this activity.
Expected Finish
The date you expect work on the activity to end.
Finish By
The date you are scheduled to complete the activity.
Finished
The date you actually completed the activity.
Log Additional Time
The amount of time you have worked on the activity since you last reported your work.
Remaining Duration
The period of time required to complete the activity based on your current work schedule and additional project commitments.
Start By
The date you are scheduled to begin the activity.
Started
The date you actually began work on the activity.
Time Spent (Labor)
The actual amount of time spent working on the activity.
Time Spent (Nonlabor)
The actual amount of time spent on the activity by a nonlabor resource.
Time Left (Labor)
The total working time left to complete the activity.
Time Left (Nonlabor)
The remaining time required of a nonlabor resource to complete the activity.