Cut and paste a work breakdown structure element
- Choose Project, WBS.
- Select the WBS element you want to cut and paste, then choose Edit, Cut.
- Select the WBS element to which you want to add the cut element, then choose Edit, Paste.
Note
- When you cut and paste a WBS element, the element's activity assignments are also pasted.
- When connected to a P6 EPPM database: When you cut and paste a WBS within the same project, the WBS, activities, and associated risks from P6 are moved; risks are not moved if you cut and paste the WBS to a different project.