Use the Select Primary Resource dialog box to select the primary resource for an activity.
Display Options bar: Lists options for changing resource columns, filters, grouping and sorting, font, and colors.
Search: Type a resource ID or name to display a filtered list of resources whose ID or name begins with this value.
Resource ID: Lists the ID of each resource in your organization.
Resource Name: Lists the name of each resource in your organization.
Primary Role: Indicates the primary role assigned to a resource.
Default Units/Time: Lists the default units/time for each resource in your organization.
Select: Applies your selection and closes this dialog box.
Clear: Removes the selected resource from your current activity.
Note
- If resource security is enabled, you can only select resources from under the resource root node you have access to or from current project resources.