Creating and Updating Schedule Sheet

A Schedule Sheet under Unifier Schedule Manager supports the following objects. For more information, refer to the Unifier User Guide, Unifier Administration Guide, and Unifier uDesigner User Guide.

Integration with P6 involves creation, modification and association of these objects automatically through Web Services calls.

As of the current Unifier release, integration with P6 Server supports the following information for each object.

To create and update these objects as part of Integration, the user must first create a data mapping relationship between data elements of Unifier and Data Elements of P6. The following section explains Data Mapping concepts and how to create one.

Apart from data mapping, Unifier should also know how to identify Activities and Resources that are coming from Primavera Project. This is to allow Unifier to support update web service method. Unifier currently supports two ways to identify an Activity and one way to identify a Resource.

An Activity can be identified by a GUID. Each activity in Primavera Project has a GUID. This GUID will be stored when an activity is created in Unifier and can be used later as part of update process.

The second way to identify an activity is through Activity ID. Each activity in Primavera Project has an Activity ID. This ID will be stored when an activity is created and will be used later as part of update process.

Resources are identified by their name. Each resource in Primavera Project has a name and this will be stored when a resource assignment is created in Unifier.