Click the corresponding button to open the Performance Percentage Completion sheet overlay in the EV Analysis log.
During each synchronization, the performance percentage completion value of an activity gets updated from P6. Unifier stores the values against corresponding data dates, which are then used to calculate earned value metrics.
Note: The functionality is only applicable to the current schedule of a project.