Scheduled Variance (SV) is the difference between the current progress and the scheduled progress of a task, in terms of cost. It is a comparison of the amount of work performed during a given period to what was scheduled to be performed. A negative variance means the project or shell is behind schedule.
SV = BCWP – BCWS
Example: $400 – $600 = –$200