Cost Performance Index (CPI) is the ratio of budgeted costs of work performed to actual costs of work performed. A value of less than 1 (less than 100%) indicates that the project or shell is over budget, and you are getting less work per dollar than planned.
CPI = BCWP/ACWP
Example: 400/750 = 0.53 or 53%