Schedule Performance Index (SPI) is the ratio of budgeted costs of work performed to budgeted costs of work scheduled. A value of less than 1 (less than 100%) indicates that the project or shell is behind schedule.
SPI = BCWP/BCWS
Example: 400/600 = 0.67 or 67%.