If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
- % Complete Calculation Method option = Manual activity % complete and resource % complete
- % Earned Calculation Method option = Manual activity % earned - updates resource % earned
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method | |
---|---|---|---|
Activity | |||
| Activity % Complete | Manual entry | |
Earned Progress | Manual entry | ||
Resource | |||
| Progress Quantity | Manual entry | |
Earned Progress | Calculated (read-only) (Activity-level Earned Progress * Quantity) |