% Earned Calculation Method option is Resource updates Activity - weighted average of resource costs

If the entry method and option settings on the Budget and Progress Method Setup window are:

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Manual entry

Earned Progress

Calculated (Weighted Cost) and read-only.

{Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

Resource

 

Progress Quantity

Manual entry

Earned Progress

Manual entry