Schedule Sheet Integration

Unifier supports out of the box (OOTB) mapping for integration between P6 and Unifier, using Schedule Sheets.

This OOTB mapping is available as part of Project Control installation as a shell template (T-002). You must create a new shell by copying shell template (T-002) in order to integrate P6 and Unifier using Schedule Sheets.

To view the data mapping fields in Unifier:

  1. Go to Company Workspace > Admin mode > Templates > Shells > Projects.
  2. Open the T-002 (Project #) Owner Project Template(Project Name).
  3. From the left-hand navigator, click Schedule Manager > Schedule Sheets.
  4. In the Schedule Sheets log, open Project Schedule Sheet.
  5. From the menu bar, click File > Data Mappings.
  6. Click P6 (to select) > Modify > Activity tab.

The column name and XML elements are listed as shown below. You can use the XML elements for integration with P6.

Column

XML Element

Activity Name

Name

Activity Percent

PercentComplete

Actual Finish Date

ActualFinishDate

Actual Start Date

ActualStartDate

Duration

PlannedDuration

Early Start date

EarlyStartDate

Early finish date

EarlyFinishDate

Finish date

PlannedFinishDate

Late Start date

LateStartDate

Late finish date

LateFinishDate

P6 Activity Number

Id

P6 CBS

CBSCode

Start date

PlannedStartDate