Auto-Scheduling of Activities

You can disable automatic re-scheduling within Unifier Schedule Sheet to:

Disabling Automatic Scheduling of Activities

When Activities with dependencies are integrated by Direct Integration with P6, or imported through MPP XMLS, the activities are re-scheduled automatically within Unifier Schedule Sheet to honor the dependencies, leading to Data change. You can disable this automatic reschedule in Schedule sheet to integrate or import the data as is and to schedule the Activities manually, if desired.

To enable or disable auto-scheduling:

  1. Go to the Schedule Sheet Properties window, General tab.
  2. Select your option in Auto-Schedule field. The default selection is Enable.

In the Schedule Sheets log, the column Auto-Schedule displays the condition of the sheet.

When the auto-scheduling is disabled:

Calendar

When the calendar that is defined for a particular Activity is changed in the Activity Properties, then Unifier changes the Finish Date. In this case, if the auto-scheduling is disabled, then no impact of this change is reflected in the dependent activities.

When the calendar that is defined for a particular Schedule Sheet is changed in the Schedule Sheet Properties, then the next time you open the schedule sheet, the following message is displayed: Schedule sheet requires a refresh due to modifications to a Calendar or Rates associated to a Role on a Resource. Do you want to refresh schedule sheet?

If you select Yes, then the schedule sheet will be rescheduled on refresh, as an impact of Calendar change, irrespective of whether Auto-scheduling is enabled or disabled.

If you select No, then no impact of Calendar change is reflected in the schedule sheet.