Manually launch a business process

When you manually launch a BP associated with an activity, you override the Auto-control property setting. See Manage scope management properties for details on properties.

See About Launching or Removing Business Processes from Activities for details on the conditions under which you can manually launch BPs.

To manually launch a BP associated with an activity

  1. In User Mode, navigate to the Schedule Manager and select Schedule Log. The Schedule Sheets log opens.
  2. Select a schedule sheet and click the Open button.
  3. Select an activity.
  4. Choose Edit > Linked Business Process > Start. You can select one or more BPs and launch them. They will be routed to the assignees that have been specified.