Remove the link between a business process and an activity

You can remove (unlink) a BP from an activity. See About Launching or Removing Business Processes from Activities for details on the conditions under which you can remove BPs from activities.

To remove the link between an activity and a BP

  1. In User Mode, navigate to the Schedule Manager and select Schedule Log. The Schedule Sheets log opens.
  2. Select a schedule sheet and click the Open button.
  3. Select an activity.
  4. Choose Edit > Linked Business Process > Remove Record. You can select one or more BPs. The BP itself is not deleted.

    Note: The link between a BP and an activity is automatically removed if the BP is terminated. When a linked BP is terminated, the BP hyperlink is removed from the associated activity, and the activity is set to not started.