Conditions for the automatic completion of activities

Unifier checks the linked BP record workflow for in-progress status activities that are not manually controlled (Auto-update Activity Data box is checked for the activity).

When the system detects BP completion based on the conditions, it performs the following actions:

  1. Actual finish is updated with current date
  2. Activity status is updated to complete
  3. Success of activities is evaluated for the automatic launching of further BPs

If there is no BP setup or if the activity is manually controlled, the system does not evaluate the BP completion conditions but waits for you to manually complete the activity.