Conditions for the manual completion of activities

Activities that are manually controlled (Auto-update Activity Data box is unchecked) can only be completed manually. In this case, you must change the activity status to Complete and enter the actual finish date, which is required for the activity to complete successfully.



Legal Notices | Your Privacy Rights
Copyright © 1998, 2022

Last Published Monday, April 11, 2022