Option | 01-09 | 02-09 | 03-09 | 04-09 | 05-09 | 06-09 | 07-09 | 08-09 | 09-09 | 10-09 | 11-09 | 12-09 |
---|---|---|---|---|---|---|---|---|---|---|---|---|
Linear | 1000 | 2000 | 3000 | 4000 | 5000 | 6000 | 7000 | 8000 | 9000 | 10000 | 11000 | 12000 |
S-Curve | 26.52 | 131.40 | 454.46 | 1243.76 | 2705.93 | 4826.86 | 7228.29 | 9349.22 | 10797.07 | 11572.10 | 11895.10 | 11999.99 |
On Start and Finish | 600 | 600 | 600 | 600 | 600 | 600 | 600 | 600 | 600 | 600 | 600 | 12000 |
To set up budget distribution for activities at the activity level
- Open a schedule sheet.
- Highlight an activity row in the sheet.
- Choose File > Budget and Progress Setup > Activity.
- Under the Activity Budget Distribution Profile section, choose an option. This option will apply specifically to the selected activity, and will override any default option set up at the schedule sheet level. The behavior of these Activity Budget Distribution Profile options at the activity level is the same as the default options at the schedule sheet level.