Select the entry method for the % complete and earned progress

You can select an entry method for the progress and earned progress data, and can enter progress (both resource and activity) and earned progress independently. Also, you can select an entry method that allows you to enter the progress of activity or resource then calculate earned progress, or enter earned progress and calculate progress for an activity or resource.

To select the entry method for the % complete and earned progress for activities at the schedule sheet level

  1. Open a schedule sheet.
  2. Choose File > Budget and Progress Setup > Schedule Sheet.
  3. In the Default % Complete and Earned Progress section, choose a default entry method. This entry method will apply to all activities in the schedule sheet, unless it is overridden by the selection of a different entry method for an individual activity.

Use this Entry Method

To do this:

Independently Control % complete and earned quantity

Enter the progress of activity or resource independent of earned progress.

Activity and resource % complete updates % earned

Enter the progress of activity or resource, and earned progress will be automatically calculated.

Activity and resource % earned updated % complete

Enter the earned progress of activity or resource, and progress will be automatically calculated.

Do not allow update of % complete and % earned

Not enter either progress or earned progress. You cannot enter any type of activity progress information with this option selected.

To select the entry method for the % complete and earned progress for activities at the activity level

  1. Open a schedule sheet.
  2. Highlight an activity row in the sheet.
  3. Choose File > Budget and Progress Setup > Activity.
  4. Under the % Complete and Earned Progress section, choose an entry method. This option will apply specifically to the selected activity, and will override any default entry method set up at the schedule sheet level. The behavior of these % Complete and Earned Progress Entry Method options at the activity level is the same as the default options at the schedule sheet level.