% Earned Calculation Method option is Manual activity % earned - updates resource % earned

If the entry method and option settings on the Budget and Progress Method Setup window are:

This data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Manual entry

Earned Progress

Manual entry

Resource

 

Progress Quantity

Calculated (read-only).

(Activity-level Activity % Complete * Quantity)

Earned Progress

Calculated (read-only).

(Activity-level Earned Progress * Quantity)