If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
- % Complete Calculation Method option = Manual activity % complete - updates resource % complete
- % Earned Calculation Method option = Resource updates Activity - weighted average of resource costs
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method |
---|---|---|
Activity | ||
| Activity % Complete | Manual entry |
Earned Progress | Calculated (Weighted Cost) {Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 | |
Resource | ||
| Progress Quantity | Calculated (read-only). (Activity-level Activity % Complete * Quantity) |
Earned Progress | Manual Entry |