If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Activity and resource % earned updates % complete
- % Complete Calculation Method option = Not available
- % Earned Calculation Method option = Update Activity and all resources on activity start and finish
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method |
---|---|---|
Activity | ||
| Activity % Complete | Calculated (read-only) Same as Earned Progress |
Earned Progress | Calculated (read-Only) based Update Activity and all resources on activity start and finish. For example: If % earned on Actual Start = 5% and % earned on Actual Finish = 95 % then, When Actual Start is entered, Earned Progress = 5% When Actual Finish is entered, Earned Progress = 100% | |
Resource | ||
| Progress Quantity | Calculated (read-only) Same as Earned Progress |
Earned Progress | Calculated (read Only) based Update Activity and all resources on activity start and finish. For example: If % earned on Actual Start = 5% and % earned on Actual Finish = 95 % then, When Actual Start is entered, Earned Progress = 5% * Quantity When Actual Finish is entered, Earned Progress = 100% * Quantity. |