Creating Schedule Manager Custom Calendars

Unifier allows you to create Custom Calendars to be used by the Schedule Manager. The Custom Calendar that you specify can override the company-level Standard Calendar. If there is no Custom Calendar, the Standard Calendar marked as the default calendar is the calendar that is used by the Schedule Manager.

Unifier allows you to create multiple Custom Calendars, enabling you to create a library of calendars that can be selected for use on your schedule sheets. The multiple calendars enable you to have calendars to support varying work schedules (depending on locality) and to account for holidays and other non-working days. For example, some countries in the Middle East have weekends that are other than Saturday and Sunday.

You must have permissions granted to create, modify, delete, or view Custom Calendars.

See Also

Unifier Schedule Manager

Schedule Sheet permissions

Create a Schedule Sheet

Add an activity to a schedule sheet

Add a schedule Sheet column

Working with Schedule Sheets

Program Schedule Sheets

Activity Sheets

Activity Sheet (Integrated with an External Application)

Using Schedule Sheets

Scope Management

Entering and Viewing Cost Data

Effects of multiple calendars

Project Progress Data Accumulation and Calculation

Progress and Earned Progress Calculations

Do not allow update of % complete and % earned

P6 Summary Sheets

Schedule Sheet Integration

Auto-Scheduling of Activities

In This Section

About Calendars and Activities

Create a custom calendar in the schedule manager



Legal Notices | Your Privacy Rights
Copyright © 1998, 2022

Last Published Monday, April 11, 2022