Unifier Schedule Manager

The Schedule Manager helps you manage project or shell and program schedules. You can create a Project Schedule Sheet that is customized to the project's needs. Once these sheets are created, you can then use them to create project activities and tasks, assign resources to tasks, create relationships between activities, track schedule progress and variables, and calculate the schedule’s critical path.

In Unifier, you can also import project schedule records from Primavera Project Planner® or Microsoft® Project. These external project schedules can provide additional detail or supporting schedule information; for example, resource information, or subcontractor or vendor schedules. Imported schedules are editable within Unifier, and the data can be used in reports.

The Schedule Manager presents schedule activities as interactive Gantt charts, where you can:

Using Unifier snapshot feature, you can take a "picture" of the schedule sheet at any point in time. Using the Schedule Manager’s baseline function, you can measure progress and determine payments against original estimates; and with the tracking Gantt feature, you can compare schedule dates, such as baseline estimates against the actual schedule.

If you copy activities from one schedule to another, Unifier will immediately notify you if the change will create a schedule conflict so that you can make corrections as you work. Each change in the Schedule Manager creates a record in Unifier, which is useful for auditing purposes. An audit report of these records shows detailed information on dates, events, actions, and old values versus new values, along with the user or proxy user who performed the action.

Each project/shell can have multiple schedule sheets, and one master schedule sheet. This master sheet drives project start and end dates, tracks the project’s progress, and serves as the interface between the Schedule Manager and other Unifier modules. In particular, the master schedule updates resource assignment information in the Resource Manager, which affects timesheets and resource utilization figures; and it integrates cost items on the schedule with the Cost Manager. Unifier users can refresh resource rates on the schedule sheet and post the new rates to the Cost Manager, update the cost sheet with assignment costs, and refresh costs on the sheet to recalculate labor costs and post them to the cost sheet.

Features include the following:

For information about language (internationalization) and CSV files refer to Unifier General User Guide.

In This Section

Schedule Sheet permissions

Create a Schedule Sheet

Add an activity to a schedule sheet

Add a schedule Sheet column

Working with Schedule Sheets

Program Schedule Sheets

Activity Sheets

Activity Sheet (Integrated with an External Application)

Using Schedule Sheets

Scope Management

Entering and Viewing Cost Data

Effects of multiple calendars

Project Progress Data Accumulation and Calculation

Progress and Earned Progress Calculations

Creating Schedule Manager Custom Calendars

Do not allow update of % complete and % earned

P6 Summary Sheets

Schedule Sheet Integration

Auto-Scheduling of Activities