Scope Management

The Scope Management defines deliverables, responsible roles, actual assignees and their schedules, and drives coordinated production of these deliverables. The Scope Management initiates actions for producing deliverables based on the completion of dependencies. It routes them to the responsible person or group, monitors their completion, and updates deliverable statuses automatically. It manages different activities across schedules for different team members simultaneously.

Team members work on BPs that are linked to activities in a schedule sheet. The Scope Management allows you to use existing schedule management functionality with added data elements to automate the management of a project’s scope and schedule with all associated activities, tasks, and deliverables. This feature provides project managers with the ability to manage each scope item’s task assignments, ownerships, and durations.

Project managers can use scope management to manage high-volume, quick turnaround projects that have standardized scope and scheduled activities. Examples of projects that would benefit from the use of scope management functionality are retail construction projects such as bank branches or chain fast food restaurants. Unifier scope management capabilities are also useful for large capital projects with complex scope and schedules, and that have numerous dependent activities and milestones with associated tasks and deadlines.

Scope management:

This functionality can be enabled on any schedule sheet, including a master schedule sheet. Scope management enables you to link BPs with schedule sheet task activities and route those BPs with an automatic update of status as they are routed and worked on. The BPs represent the work that needs to be done to complete the task. You can override automatic routing at any time and launch the BPs manually. The BP-related task is completed when specified conditions are met.

See Also

Unifier Schedule Manager

Schedule Sheet permissions

Create a Schedule Sheet

Add an activity to a schedule sheet

Add a schedule Sheet column

Working with Schedule Sheets

Program Schedule Sheets

Activity Sheets

Activity Sheet (Integrated with an External Application)

Using Schedule Sheets

Entering and Viewing Cost Data

Effects of multiple calendars

Project Progress Data Accumulation and Calculation

Progress and Earned Progress Calculations

Creating Schedule Manager Custom Calendars

Do not allow update of % complete and % earned

P6 Summary Sheets

Schedule Sheet Integration

Auto-Scheduling of Activities

In This Section

Working with Schedule Sheets with Scope Management

Launching Business Processes from Activities

Status Transitions and Activities

About Launching or Removing Business Processes from Activities

About Activity Completion

About Manual or Automatic Control of Individual Activities

Impact of Schedule Start Date

Calculation of Estimated Start and Finish Dates

Impact of Successor and Predecessor Activities on Launching and Completion of BPs