Completed Before Outage Project Snapshot Use Case

This use case describes what happens when an activity completes before the Outage Project Snapshot is taken.

P6 Values Table

Field

Planned Value

Actual Value

Start

3/30/2013 12:00 a.m.

3/30/2013 12:00 a.m.

Finish

3/30/2013 10:00 a.m.

3/30/2013 10:00 a.m.

Duration

10 hours

10 hours

Units

10

10

Burn Down Results

3/31: Only the Actual Units Burn values will be captured in Burn Down because the activity was completed before the snapshot date of 3/31/2013.

Day

Remaining Units Burn

Actual Units Burn

Completed

Emergent Count

Day 0 (3/31)

0

10

0

0

Day 1 (4/1)

0

10

0

0

Day 2 (4/2)

0

10

0

0

Day 3 (4/3)

0

10

0

0

Note: These activities can be filtered with Oracle Business Intelligence.