This use case describes what happens when an activity completes before the Outage Project Snapshot is taken.
P6 Values Table
Field | Planned Value | Actual Value |
---|---|---|
Start | 3/30/2013 12:00 a.m. | 3/30/2013 12:00 a.m. |
Finish | 3/30/2013 10:00 a.m. | 3/30/2013 10:00 a.m. |
Duration | 10 hours | 10 hours |
Units | 10 | 10 |
Burn Down Results
3/31: Only the Actual Units Burn values will be captured in Burn Down because the activity was completed before the snapshot date of 3/31/2013.
Day | Remaining Units Burn | Actual Units Burn | Completed | Emergent Count |
---|---|---|---|---|
Day 0 (3/31) | 0 | 10 | 0 | 0 |
Day 1 (4/1) | 0 | 10 | 0 | 0 |
Day 2 (4/2) | 0 | 10 | 0 | 0 |
Day 3 (4/3) | 0 | 10 | 0 | 0 |
Note: These activities can be filtered with Oracle Business Intelligence.