This use case describes what happens when an activity starts before the sys_workdown_date and ends after the Outage Project Snapshot is taken, on Day 1.
P6 Values Table
Field | Planned Value | Actual Value |
---|---|---|
Start | 3/30/2013 12:00 a.m. | 3/30/2013 12:00 a.m. |
Finish | 4/01/2013 2:00 a.m. | 4/01/2013 2:00 a.m. |
Duration | 50 hours | 50 hours |
Units | 50 | 50 |
Burn Down Results
- 3/31: When the ETL process runs, this activity has only two Remaining Units and it is scheduled to finish on Monday 4/01/2013 (Day 1).
- 4/01: The activity is completed in P6 on 4/01 and then it is counted as complete when the ETL runs on 4/01. The Actual Units Burn value of 50 will continue to be captured after completion so Cumulative Totals can be counted by day.
Day | Remaining Units Burn | Actual Units Burn | Completed | Emergent Count |
---|---|---|---|---|
Day 0 (3/31) | 2 | 48 | 0 | 0 |
Day 1 (4/01) | 0 | 50 | 1 | 0 |
Day 2 (4/02) | 0 | 50 | 0 | 0 |
Day 3 (4/03) | 0 | 50 | 0 | 0 |