Completed Day of Outage Project Snapshot Use Case

This use case describes what happens when an activity starts and completes on the project snapshot date.

P6 Values Table

Field

Planned Value

Actual Value

Start

3/31/2013 12:00 a.m.

3/31/2013 12:00 a.m.

Finish

3/31/2013 10:00 a.m.

3/31/2013 10:00 a.m.

Duration

10 hours

10 hours

Units

10

10

Burn Down Results

3/31: The activity is completed in P6 and counted as complete when the ETL process runs. The Actual Units Burn value of 10 will continue to be captured after completion so Cumulative Totals can be counted by day.

Day

Remaining Units Burn

Actual Units Burn

Completed

Emergent Count

Day 0 (3/31)

0

10

1

0

Day 1 (4/01)

0

10

0

0

Day 2 (4/02)

0

10

0

0

Day 3 (4/03)

0

10

0

0