This use case describes what happens when an activity starts and completes on the project snapshot date.
P6 Values Table
Field | Planned Value | Actual Value |
---|---|---|
Start | 3/31/2013 12:00 a.m. | 3/31/2013 12:00 a.m. |
Finish | 3/31/2013 10:00 a.m. | 3/31/2013 10:00 a.m. |
Duration | 10 hours | 10 hours |
Units | 10 | 10 |
Burn Down Results
3/31: The activity is completed in P6 and counted as complete when the ETL process runs. The Actual Units Burn value of 10 will continue to be captured after completion so Cumulative Totals can be counted by day.
Day | Remaining Units Burn | Actual Units Burn | Completed | Emergent Count |
---|---|---|---|---|
Day 0 (3/31) | 0 | 10 | 1 | 0 |
Day 1 (4/01) | 0 | 10 | 0 | 0 |
Day 2 (4/02) | 0 | 10 | 0 | 0 |
Day 3 (4/03) | 0 | 10 | 0 | 0 |