Pre-Outage Work Spanning into Outage Use Case

This use case describes what happens when an activity starts on the project snapshot date and completes on Day 1 of the outage.

P6 Values Table

Field

Planned Value

Actual Value

Start

3/31/2013 12:00 a.m.

3/31/2013 12:00 a.m.

Finish

4/01/2013 6:00 a.m.

4/01/2013 6:00 a.m.

Duration

30 hours

30 hours

Units

30

30

Burn Down Results

Day

Remaining Units Burn

Actual Units Burn

Completed

Emergent Count

Day 0 (3/31)

6

24

0

0

Day 1 (4/1)

0

30

1

0

Day 2 (4/2)

0

30

0

0

Day 3 (4/3)

0

30

0

0