This use case describes what happens when an activity starts on the project snapshot date and completes on Day 1 of the outage.
P6 Values Table
Field | Planned Value | Actual Value |
---|---|---|
Start | 3/31/2013 12:00 a.m. | 3/31/2013 12:00 a.m. |
Finish | 4/01/2013 6:00 a.m. | 4/01/2013 6:00 a.m. |
Duration | 30 hours | 30 hours |
Units | 30 | 30 |
Burn Down Results
- 3/31: When the ETL process runs, this activity will have six Remaining Units and it will be scheduled to finish on Monday 4/01/2013 (Day 1).
- 4/01: The activity is completed in P6 and then it is counted as complete when the ETL process runs. The Actual Units Burn value of 30 will continue to be captured after completion so Cumulative Totals can be counted by day.
Day | Remaining Units Burn | Actual Units Burn | Completed | Emergent Count |
---|---|---|---|---|
Day 0 (3/31) | 6 | 24 | 0 | 0 |
Day 1 (4/1) | 0 | 30 | 1 | 0 |
Day 2 (4/2) | 0 | 30 | 0 | 0 |
Day 3 (4/3) | 0 | 30 | 0 | 0 |