Completed as Scheduled on Day 1 of Outage Use Case

This use case describes what happens when an activity starts and completes as scheduled on Day 1 of the outage.

P6 Values Table

Field

Planned Value

Actual Value

Start

4/01/2013 12:00 a.m.

4/01/2013 12:00 a.m.

Finish

4/01/2013 10:00 a.m.

4/01/2013 10:00 a.m.

Duration

10 hours

10 hours

Units

10

10

Burn Down Results

Day

Remaining Units Burn

Actual Units Burn

Completed

Emergent Count

Day 0 (3/31)

10

10

1

0

Day 1 (4/01)

0

10

0

0

Day 2 (4/02)

0

10

0

0

Day 3 (4/03)

0

10

0

0



Legal Notices | Your Privacy Rights
Copyright © 2013, 2020

Last Published Monday, December 14, 2020