This use case describes what happens when an activity starts on Day 2 and additional Remaining Units and Duration are added to the activity causing it to not finish as scheduled. In this use case, the activity finishes on the following day, 4/03/2013.
P6 Values Table
Field | Planned Value | Actual Value |
---|---|---|
Start | 4/02/2013 12:00 a.m. | 4/02/2013 12:00 a.m. |
Finish | 4/02/2013 10:00 a.m. | 4/03/2013 6:00 a.m. |
Duration | 10 hours | 30 hours |
Units | 10 | 30 (+20) |
Burn Down Results
- 3/31: When the ETL process runs, this activity has 10 Remaining Units and it is scheduled to finish on Monday 4/02/2013 (Day 2).
- 4/01: When the ETL process runs, this activity still has 10 Remaining Units and is scheduled to finish on Monday 4/02/2013 (Day 2).
- 4/02: The activity has 20 additional units added.
- The Remaining Units Burn increases from 0 to 6.
- Actual Units Burn increases from 10 to 24.
- 4/03: The activity is completed in P6 and counted as complete when the ETL process runs.
Day | Remaining Units Burn | Actual Units Burn | Completed | Emergent Count |
---|---|---|---|---|
Day 0 (3/31) | 10 | 0 | 0 | 0 |
Day 1 (4/01) | 10 | 0 | 0 | 0 |
Day 2 (4/02) | 6 | 24 | 0 | 0 |
Day 3 (4/03) | 0 | 30 | 1 | 0 |