Completed Late on Day 3 of Outage Use Case

This use case describes what happens when an activity starts on Day 2 and additional Remaining Units and Duration are added to the activity causing it to not finish as scheduled. In this use case, the activity finishes on the following day, 4/03/2013.

P6 Values Table

Field

Planned Value

Actual Value

Start

4/02/2013 12:00 a.m.

4/02/2013 12:00 a.m.

Finish

4/02/2013 10:00 a.m.

4/03/2013 6:00 a.m.

Duration

10 hours

30 hours

Units

10

30 (+20)

Burn Down Results

Day

Remaining Units Burn

Actual Units Burn

Completed

Emergent Count

Day 0 (3/31)

10

0

0

0

Day 1 (4/01)

10

0

0

0

Day 2 (4/02)

6

24

0

0

Day 3 (4/03)

0

30

1

0