This use case describes what happens when an activity is added to the schedule on Day 2 and completed on Day 3.
P6 Values Table
Field | Planned Value | Actual Value |
---|---|---|
Start | 4/03/2013 12:00 a.m. | 4/03/2013 12:00 a.m. |
Finish | 4/03/2013 10:00 a.m. | 4/03/2013 10:00 a.m. |
Duration | 10 hours | 10 hours |
Units | 10 | 10 (+10) |
Burn Down Results
- 4/02: The activity is added and scheduled to complete on 4/03.
- Remaining Units Burn = 10
- Emergent Count = 1
- 4/03: The activity is completed in P6 and counted as complete when the ETL process runs.
Day | Remaining Units Burn | Actual Units Burn | Completed | Emergent Count |
---|---|---|---|---|
Day 0 (3/31) | 0 | 0 | 0 | 0 |
Day 1 (4/01) | 0 | 0 | 0 | 0 |
Day 2 (4/02) | 10 | 0 | 0 | 1 |
Day 3 (4/03) | 0 | 10 | 1 | 0 |