Emergent Activity on Day 3 of Outage Use Case

This use case describes what happens when an activity is added to the schedule on Day 2 and completed on Day 3.

P6 Values Table

Field

Planned Value

Actual Value

Start

4/03/2013 12:00 a.m.

4/03/2013 12:00 a.m.

Finish

4/03/2013 10:00 a.m.

4/03/2013 10:00 a.m.

Duration

10 hours

10 hours

Units

10

10 (+10)

Burn Down Results

Day

Remaining Units Burn

Actual Units Burn

Completed

Emergent Count

Day 0 (3/31)

0

0

0

0

Day 1 (4/01)

0

0

0

0

Day 2 (4/02)

10

0

0

1

Day 3 (4/03)

0

10

1

0